Cases : Total Wholsale is equipped with multiple cold storage units. Electrical system is based on a 3 Phase System. In a case like this where energy consumption is above a certain amps, JPS uses a demand charge system based on overall power factor.

 

Recommendation : We did an analsyis for compressor units and recommended that capacitor units be installed to increase the power factor to as close as 0.99, therefore reducing the energy consumption of compressor units.

 

Results: We designed capacitor banks for two of the units at location and installed. The results were as expected. On one unit energy consumption was reduced by 18 amps which results in a 4kw reduction per hour at 220v.

Where to Find Us:

Shop 1 Q Ville Plaza

5-7 Villa Road (Beside JPS)
Mandeville P.O.

Manchester

 

Telephone :  

876-632-GSEP (4737)

876-622-4834

 

What's New

Extended business hours

To accomodate our customers' busy schedules, we have extended our hours and are now open later.

 

Mondays - Fridays

    9am - 5:00pm

      

Print Print | Sitemap Recommend this page Recommend this page
Green Sun Energy Plus Limited 2017